Frank Miller Frank Miller
0 Course Enrolled • 0 Course CompletedBiography
C_TS422_2023 Exam Labs | C_TS422_2023 Simulations Pdf
What's more, part of that Prep4sures C_TS422_2023 dumps now are free: https://drive.google.com/open?id=1nXP6p-6jk_Qwwm5SsAUA-yJ4jBm8H2Q6
So many candidates have encountered difficulties in preparing to pass the C_TS422_2023 exam. But our study materials will help candidates to pass the exam easily. Our C_TS422_2023 guide questions can provide statistics report function to help the learners to find weak links and deal with them. The C_TS422_2023 Test Torrent boost the function of timing and simulating the exam. They set the timer to simulate the exam and help the learners adjust the speed and keep alert. So the C_TS422_2023 guide questions are very convenient for the learners to master and pass the exam.
As a responsible company, we don't ignore customers after the deal, but will keep an eye on your exam situation. Although we can assure you the passing rate of our C_TS422_2023 training guide nearly 100 %, we can also offer you a full refund if you still have concerns. So you have nothing to worry about, only to study with our C_TS422_2023 Exam Questions with full attention. And as we have been in this career for over ten years, our C_TS422_2023 learning materials have became famous as a pass guarantee.
SAP C_TS422_2023 PDF Questions - Most Effective Exam Preparation Method
If you decide to buy our C_TS422_2023 study questions, you can get the chance that you will pass your exam and get the certification successfully in a short time. we can claim that if you study with our C_TS422_2023 exam questions for 20 to 30 hours, then you will be easy to pass the exam. In a word, if you want to achieve your dream and become the excellent people in the near future, please buy our C_TS422_2023 Actual Exam, it will help you get all you want!
SAP S/4HANA Cloud Private Edition - Production Planning and Manufacturing Sample Questions (Q21-Q26):
NEW QUESTION # 21
During production order creation several valid production versions are found. How does the system choose the production version?
- A. Alphanumeric or quota arrangement
- B. Validity period or sales order
- C. Lot size or material cost
- D. Planned order or material number
Answer: A
NEW QUESTION # 22
Which time elements can be reduced by a reduction strategy?
Note: There are 3 correct answers to this question.
- A. Queue time
- B. Wait time
- C. Float after production
- D. Goods receipt processing time
- E. Move time
Answer: A,B,E
Explanation:
A reduction strategy is a method of shortening the lead time of an order by reducing certain time elements in the order scheduling1. The time elements that can be reduced by a reduction strategy are move time, wait time, and queue time2. Move time is the time required to move a material from one operation to another. Wait time is the time between the end of an operation and the start of the next operation. Queue time is the time before an operation can start at a work center due to the work center's capacity utilization3. These time elements can be reduced by a percentage or a fixed value in the reduction strategy. Reference: 1: Reduction Strategy | SAP Help Portal(https://blog.sap-press.com/4-strategies-for-make-to-stock-production-with-sap-s4hana)2: 4 Strategies for Make-to-Stock Production with SAP S/4HANA(https://blogs.sap.com/2022/03/22/highlights-for-manufacturing-in-sap-s-4hana-2021-part-2-production-planning-engineering-operations/)3: Scheduling | SAP Help Portal(https://blogs.sap.com/2022/04/26/manufacturing-in-sap-s-4hana-cloud-planning-strategies/).
NEW QUESTION # 23
Your quality department detects a deviation in a raw material batch. Unfortunately this batch has already been used in production. How can you identify all affected finished goods stocks?
Note: There are 2 correct answers to this question.
- A. Use the Batch Information Cockpit.
- B. Use the batch whereused list.
- C. Use batch derivation.
- D. Use batch determination.
Answer: A,B
NEW QUESTION # 24
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements
- B. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run
- C. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements
- D. An evaluation to verify if there are material or capacity shortages in the